Try it yourself · Class 8 Maths · Direct and Inverse Variations
Working together: change the days of A, B and the time worked
If a worker takes more days, the work done each day is less. This is inverse variation. When two people work together, the part of the job they do in one day adds up. The simulation shows the time together as a bar that is shorter than either bar alone.
Rates add: together take days.
The simulation needs JavaScript; everything it shows is explained below.
What to change
- Slide the days A takes alone from 2 to 30.
- Slide the days B takes alone from 2 to 30.
- Slide the days together from 0 to 20.
- Make A and B equal.
What to watch
- At the start A takes 12 days and B takes 15 days. Together they take 6.67 days.
- The rates add: 1/12 + 1/15 = 0.133 of the job each day.
- After 3 days together, 3 × 0.133 = 0.4, so the bar shows 40% of the job. After 8 days it shows 100%.
- Make both 10 days. Together they take 5 days, which is half of 10.
- Set A to 2 and B to 30. Together they take 1.88 days, which is less than the faster worker alone.
The formula
and are the days taken alone. A does of the job in a day and B does , so together they do of the job in a day.
Try these questions
Work each one out with the simulation, tap to see the answer, then try the chapter quiz.
-
NCERT
A swimming pool can be filled in 4 hours by 8 pumps of the same type. How many such pumps are required if the pool is to be filled in hours?Show the answer
12 pumps -
NCERT
30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?Show the answer
21 person